From: Harry Rööpson

Company: NOBE

Role: Construction

"The team worked with youthful energy and strong motivation, balancing demanding moments with a healthy dose of humour."

Work & Approach

As with any construction project, progress relied on a phased approach. We began with the underground level, continued with the above-ground structural frame and concluded with interior works. Due to the project’s complex interior solutions, each stage required careful joint planning with the client. One of the key efforts was ensuring that the building reached full waterproofing quickly, including the rooms located below ground. Not easy, but done.

Breakthroughs

The most significant challenge was managing the construction design process in the context of the project’s scale and complexity: creating the -1 level between historic limestone walls, supporting existing tunnels, executing intricate balcony and structural junction details and maintaining precise craftsmanship throughout. Adhering to the schedule remained critically important from start to finish.

Takeaways

Meticulously planned ceiling systems, movement routes and accessibility solutions form the foundation for a functional and future-proof building. Difficult to put into words, really. Close collaboration with the designers was essential to ensure that the complex structural solutions work seamlessly and that the end user would receive a safe and comfortable environment.

Facts

The building was constructed between existing limestone walls, including a -1 level

  • Sustainability and environmental footprint were key considerations; the building complies with certification requirements

  • The project is used as a reference: active knowledge-sharing with industry peers and strong market interest

From: Harry Rööpson

Company: NOBE

Role: Construction

"The team worked with youthful energy and strong motivation, balancing demanding moments with a healthy dose of humour."

Work & Approach

As with any construction project, progress relied on a phased approach. We began with the underground level, continued with the above-ground structural frame and concluded with interior works. Due to the project’s complex interior solutions, each stage required careful joint planning with the client. One of the key efforts was ensuring that the building reached full waterproofing quickly, including the rooms located below ground. Not easy, but done.

Breakthroughs

The most significant challenge was managing the construction design process in the context of the project’s scale and complexity: creating the -1 level between historic limestone walls, supporting existing tunnels, executing intricate balcony and structural junction details and maintaining precise craftsmanship throughout. Adhering to the schedule remained critically important from start to finish.

Takeaways

Meticulously planned ceiling systems, movement routes and accessibility solutions form the foundation for a functional and future-proof building. Difficult to put into words, really. Close collaboration with the designers was essential to ensure that the complex structural solutions work seamlessly and that the end user would receive a safe and comfortable environment.

Facts

The building was constructed between existing limestone walls, including a -1 level

  • Sustainability and environmental footprint were key considerations; the building complies with certification requirements

  • The project is used as a reference: active knowledge-sharing with industry peers and strong market interest